It was critical that the secured premises remained fully operational during the works. The Langley system allowed for the existing roof to be overlaid and the liquid system ensured that the roof remained fully watertight throughout all stages of installation.
Contractor:
Acclaim Contracts Ltd
Consultant:
J. Dunton Associates Ltd
System Used:
Langley’s Paracoat Liquid Roofing System
The building owner sourced J. Dunton Associates Ltd to lead the project and approached Langley to carry out an extensive roof condition survey on the premises’ estate.
The Task
The survey detailed that the existing single ply system was reaching the end of it’s life. Langley then created a comprehensive roof specification which was finalised and agreed by J. Dunton Associates Ltd. Acclaim Contracts were then appointed to complete the roof refurbishments.
The Outcome
“Langley’s system was high quality and worked extremely well on the roofs. It left a neat finish and had a high durable strength. All parties where extremely happy with the completed installation”.
Reece Spurr, Acclaim Contracts, Contracts Manager